What the I-35 Rebuild Means for Each Side of Travis Heights Through 2033

November 19, 2026

On the nights of November 9 and 10, TxDOT closed Woodland Avenue at the southbound I-35 frontage road from 10 p.m. to 5 a.m. for survey work. A notice on the South River City Citizens listserv sent drivers around it on Travis Heights Boulevard and Oltorf Street. The rebuild reaches Travis Heights from the frontage road, and on nights like those its detours run up streets inside the neighborhood.

For a buyer comparing Travis Heights with other central neighborhoods, the median price on a portal tells you very little about this. The I-35 Capital Express Central project runs along the neighborhood's eastern side, where the highway crossings are at Riverside Drive, Woodland Avenue and Oltorf Street. TxDOT has published dates for its pieces, and those dates fall into two groups. Some of the disruption ends in 2029, the rest by 2033, and two changes are permanent. A house four blocks from the frontage road and a house on it are the same purchase under different schedules. Your holding period decides which schedule matters to you.

The segment, and the date that frames everything else

TxDOT calls this stretch the Lady Bird Lake segment, running from Holly Street to SH 71/Ben White Boulevard. The plan adds two high-occupancy-vehicle managed lanes in each direction, rebuilds the Lady Bird Lake bridge and turns Riverside Drive into a single-point urban interchange designed to accommodate future city light rail. Balfour Beatty Construction is the contractor. TxDOT's anticipated completion is 2033, weather permitting. TxDOT's technical schedule, last updated September 2, 2026, also shows the segment in construction through 2033.

A buyer who closes this winter on a five-year plan will own the house for the whole build and sell into the final years of construction. On a ten-year plan, the last few years of ownership fall after the project is done. Neither plan is wrong. They make the same address a different purchase.

Riverside Drive: the north end, on a clock that runs to 2033

Riverside is the northern crossing for Travis Heights, and TxDOT has published its order of work. According to the Riverside Drive fact sheet, crews work on the north side of the bridge in mid-2026 and move to the middle of the intersection in mid-2027. From 2028 through 2033 they demolish the old bridge and build the new south side, and traffic then switches to the finished interchange.

The detours are already in place. TxDOT's segment page says access to the northbound frontage road just north of Riverside is closed through 2029. Drivers on Riverside who want to go north take the southbound frontage road, U-turn at Woodland Avenue and use a Riverside bypass lane to reach the northbound frontage road. Southbound frontage traffic just north of Riverside also uses a bypass lane and a temporary signal through 2029. In February, the Austin American-Statesman reported that the northbound Riverside exit, Exit 233, and the Holly Street entrance and exit, Exit 234A, had closed permanently and a new Holly Street exit had opened. That same month, KXAN interviewed Riverside residents who described the U-turn routing as difficult and frustrating.

The construction affects walking and lake access too. The existing east pedestrian path at Lady Bird Lake and the north sidewalk on Riverside are closed through 2029. Boat passage under the I-35 bridge is limited to a 75-foot-wide channel through 2033. For a household on the northern blocks that walks to the lake every morning, the 2029 date matters more than any other on the calendar.

Woodland Avenue: the one change that does not end

Most of the dates above describe how long a detour lasts. Woodland's closure is permanent. TxDOT's segment page says Woodland Avenue under I-35 is permanently closed. Drivers on Woodland now detour to Riverside or Oltorf.

KUT reported the closure in January. The South River City Citizens Neighborhood Association, which represents residents on both sides of the highway, had opposed it since the proposal first surfaced in 2013. KUT noted that Austin City Council, in a 2023 vote, said the closure "creates a division in the city of more than a mile between the Riverside Drive and Oltorf Street crossings." At the time of KUT's report, the recommended walking detour uphill to Oltorf and back down to Woodland was more than a mile.

The crossing that replaces it will carry people on foot and on bikes. TxDOT is paying for a 75-foot-wide pedestrian and bicycle bridge at Woodland, after Council considered and rejected spending at least $15 million on a 300-foot-wide version. KUT reported that construction could start as soon as 2029. The temporary U-turn lanes at the underpass will go away once TxDOT lowers the I-35 mainlanes. In 2024, the Austin Monitor reported that TxDOT had moved the bridge's alignment closer to Woodland after complaints from residents and the city.

For a buyer on the blocks near Woodland, this splits into two separate questions. The car trip east has changed for good, and every crossing by car now goes through Riverside or Oltorf. The walk or ride east depends on a bridge whose construction may start in 2029, so the opening day falls later still.

Oltorf and the southern blocks: the quieter end of the schedule

At the southern end, the plan reaches further back. In 2024, the Austin Monitor reported that the Oltorf bridge had already been widened in 2020 and was not slated for substantial new bridge work in this project. TxDOT's construction summary groups the nearby work into phases. Phase I builds the northbound frontage road, closes the southbound Woodland exit and builds a shared-use path from Woodward Street to Ben White. Phase II rebuilds southbound I-35 south of Oltorf, demolishes the Woodland Avenue I-35 bridge and adds a braided southbound ramp south of Oltorf. Phase III builds the Woodland pedestrian bridge.

On the published phases, Oltorf is the steadier southern crossing while Riverside is rebuilt to the north. With Woodland closed to cars, Oltorf and Riverside are the two crossings TxDOT's detours name.

What the edge of the neighborhood will feel like, day to day

TxDOT's guide to the Lady Bird Lake segment tells nearby residents to expect construction noise, vibration, dust, lighting and delays. It also warns of more traffic on frontage roads and neighborhood streets, with work during the day, at night and on weekends. Its listed noise measures are temporary barriers, advance notices and limits on work hours. The neighborhood association has described the effect in plain terms. SRCC's April 2026 newsletter said the I-35 approval "dramatically impacted our traffic patterns," and noted that the association had grown by at least 60 members since the previous spring.

The finished project will not include any cap over the highway near Travis Heights. As Community Impact reported in July, the city's cap-and-stitch plan covers three downtown caps between Cesar Chavez and 12th streets and two stitches from 41st Street to the Red Line. City Council finalized its commitment of $104 million for the caps' foundations, and letting for that work could begin in fall 2028. The new noise wall reported this summer is a 21-foot wall on the northbound frontage road between 30th and 38½ streets, far north of the neighborhood.

Reading a Travis Heights address against the calendar

Put the published dates together and the eastern edge of Travis Heights splits into three zones, each with its own schedule. The northern blocks near Riverside follow the interchange schedule. Detours run through 2029, and the switch to the finished interchange happens somewhere in the 2028 to 2033 window. The blocks near Woodland have already absorbed their permanent change, the loss of the car crossing, and are waiting on a bridge for walkers and cyclists whose construction could begin in 2029. The southern blocks near Oltorf face the least bridge work on the published plan and serve as the main crossing for cars.

Moving west toward South Congress, each of these schedules matters less, because the street grid stands between the house and the frontage road. For a buyer who wants Travis Heights' trees, lot sizes and walk to the lake, the way to match a block to a plan is to set two dates side by side: the date the relevant piece of I-35 work finishes, and the date you expect to sell. Our earlier guide to buying in Travis Heights covers the lot and tree questions that come next.

A few questions buyers ask about the eastern edge

Will Woodland Avenue ever reopen to cars under I-35? No. TxDOT lists the vehicle closure as permanent, and the planned replacement is a 75-foot bridge for pedestrians and cyclists.

When does the Riverside detour end? TxDOT lists the frontage-road shifts and the northbound frontage closure just north of Riverside through 2029. Traffic moves onto the finished interchange at the end of the 2028 to 2033 phase.

Is any part of the downtown deck plan near Travis Heights? No. The planned caps sit between Cesar Chavez and 12th streets, and the stitches run from 41st Street to the Red Line.

If you're weighing two Travis Heights homes a few blocks apart, Anna Morrison Lee is glad to talk through where each one sits on TxDOT's Riverside, Woodland and Oltorf schedule, and how that lines up with how long you plan to stay, before you write an offer. Schedule a private consultation.